Current roadmap issues: Roadmap
- Issue == (bug or feature), that could become part of the roadmap and label it "ROADMAP"
- Important bugs are not voted, but directly fixed
- Alternative : send email to Julien and Michael
- as agreed by the consortium, as our GitHub is public, the discussions on roadmap issues are open and anybody (members and not-members) can propose issues for the roadmap and take part in the discussions on the issues, to state its opinion
- State: specification
- List of issues send to members, wait 4 weeks to complete with ideas
- Members and Inria declare issues interesting for them
- Collect ideas of all members and affine them
- Developers complete and estimate items identified as interesting for members
- State: estimated
- Developers estimate potential development volume for this vote, as updates and fixes might be necessary, that will require time too
- Only estimated and fully specified issues come to the vote
- Voting for roadmap of 6 months (01.07. - 31.12.2022)
- Summary of completed list, send for vote
- 2 weeks for votes
- State: voted
- Summary of vote shared by developers
- Issue is labelled with a release version and a date, when it comes
- Development starts
- States: development, review, test
Documentation is done for each issue, when released, added to release notes
- States: documentation and production
-
specification -> GitHub issue created and tagged with "ROADMAP"
-
estimated Issue has been identified as interesting by at least one member and will therefore be finished as specification and estimated in terms of dev effort.
-
voted An issue has officially been voted on the roadmap and will be tagged with an upcoming release number and date, when it will be released.
-
development dev only starts, when item has been voted by the consortium members
-
review PR in review from another developer
-
test (in develop, but not yet in master) often on qualif env, for test
-
documentation extend GitHub Wiki to complete doc on new feature
-
production part of master and added to release notes
Dev efforts in t-shirt sizes:
- [S]: 1-3 work days
- [M]: 4-5 days (1 week)
- [L]: 6-10 days (2 weeks)
- [XL]: 11-20 days (4 weeks)
- [XXL]: 21-40 days (2 months)
- [XXXL]: 40+ days (> 2 months)