fix errors
Browse files Browse the repository at this point in the history
*Fix recovery plot plotting and scale
*Add explanation for B0 histogram issue #5
  • Loading branch information
brianlangseth-NOAA committed Apr 12, 2024
1 parent 7dedf43 commit 8e1bed7
Showing 1 changed file with 18 additions and 12 deletions.
30 changes: 18 additions & 12 deletions R/DoProjectPlots.R
Original file line number Diff line number Diff line change
Expand Up @@ -130,6 +130,10 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
}
# ==================================================================================================

#This figure comes from x and y values that rebuilder outputs into res.csv. Sometimes the x range that rebuilder
#outputs doesn't cover the full range of values for B0, thus the histogram is bunched up at the margins.
#This would need to confirmed and corrected within the fortran rebuilder code. I have not done that.
#In the meantime, beware that the histogram may look off because its bunched up.
B0Dist <- function(UUU, Title) {
par(mfrow = c(Outlines[1], Outlines[2]))

Expand Down Expand Up @@ -414,7 +418,7 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
col2 <- c(col2, ColorsUsed[IlineType])
}

legend(LegLoc, legend = legs, lty = Ltys, cex = 1, col = col2, lwd = lwd)
legend(LegLoc, legend = legs, lty = Ltys, cex = 1, col = col2, lwd = lwd, bty = "n")
for (i in 1:4) if (!is.null(AltStrat.output[[i]])) names(AltStrat.output[[i]])[-1] <- legs

return(AltStrat.output)
Expand All @@ -425,7 +429,8 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
# This function makes plots of confidence intervals of individual trajectories for the strategy
# specified in the Rebuild.dat file ("Which probability to produce detailed outputs for")
# Lines are at the 5th and 95th percentile (light gray), 25th and 75th percentile (dark gray),
# and 50th percentile (solid line)
# and 50th percentile (solid line).
# Horizontal dashed lines on Spawning Biomass plot are 40 and 25 percent of unfished biomass
par(mfrow = c(OutlineMulti[1], OutlineMulti[2]))

Ipnt <- which(UUU == "#Individual") + 2
Expand Down Expand Up @@ -537,7 +542,7 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
FinalRecovery <- function(UUU, Title) {
# This function plots a histogram of the time to first reach recovery for each simulation from the
# strategy specified in the Rebuild.dat file ("Which probability to produce detailed outputs for")
# along with a dashed vertical line indicating Tmax.
# along with a dashed vertical line indicating Tmax. The histogram is scaled so the values sum to 1
#
# In addition this function plots the probability for each year that the target was reached
# (red line, i.e. cumulative distribution of the histogram) and the probability for
Expand All @@ -554,26 +559,27 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
Xvals <- as.double(UUU[Ipnt:(Ipnt + Npnt - 1), 1])
Yvals <- as.double(UUU[Ipnt:(Ipnt + Npnt - 1), 3])
ymax <- max(Yvals)
plot(Xvals, Yvals, xlab = "Year", ylab = "Proportion of Simulations", type = "n", yaxs = "i", ylim = c(0, 1.4 * ymax))
plot(Xvals, Yvals, xlab = "Year", ylab = "Proportion of Simulations", type = "n", yaxs = "i", ylim = c(0, 1.4 * ymax/sum(Yvals)))

Inc <- (Xvals[2] - Xvals[1]) / 2
for (II in 1:Npnt)
{
xx <- c(Xvals[II] - Inc, Xvals[II] - Inc, Xvals[II] + Inc, Xvals[II] + Inc)
yy <- c(0, Yvals[II], Yvals[II], 0)
yy <- c(0, Yvals[II]/sum(Yvals), Yvals[II]/sum(Yvals), 0)
polygon(xx, yy, col = "gray")
}
Yvals <- match(1, as.double(UUU[Ipnt:(Ipnt + Npnt - 1), 6]))
abline(v = Yvals + Inc, lty = 2, lwd = 3, col = "black")
tmax <- as.double(UUU[which(UUU == "#Recovery_Spec")+2,1])
abline(v = tmax, lty = 2, lwd = 3, col = "black")
title(Title)

Yvals_first <- as.double(UUU[Ipnt:(Ipnt + Npnt - 1), 4])
first_max <- max(Yvals_cum)
first_max <- max(Yvals_first)
Yvals_current <- as.double(UUU[Ipnt:(Ipnt + Npnt - 1), 5])
current_max <- max(Yvals_current)
par(new = TRUE)
plot(Xvals, Yvals_cum / cum_max, type = "l", lty = 1, lwd = 5, col = "red",
axes = FALSE, bty = "n", xlab = "", ylab = "")
lines(Xvals, Yvals_current / first_max, lty = 1, lwd = 5, col = 4)
plot(Xvals, Yvals_first / first_max, type = "l", lty = 1, lwd = 5, col = "red",
axes = FALSE, bty = "n", xlab = "", ylab = "", yaxs = "i")
lines(Xvals, Yvals_current / current_max, lty = 1, lwd = 5, col = 4)
axis(side = 4)
mtext("Cumulative Probability", side = 4, line = 3)

Expand All @@ -583,7 +589,7 @@ DoProjectPlots <- function(dirn = "C:/myfiles/", fileN = c("res.csv"), Titles =
}
# ==================================================================================================
# make empty list
UUUs <- vector("list", 5)
UUUs <- vector("list", 5) #<- This may throw an error if length of dirn is greater than one
# number of files to read
Nfiles <- length(fileN)
# if only 1 directory was input, repeat for each file
Expand Down

0 comments on commit 8e1bed7