Notifications
You must be signed in to change notification settings - Fork 358
Commit
This commit does not belong to any branch on this repository, and may belong to a fork outside of the repository.
- Loading branch information
Showing
1 changed file
with
42 additions
and
0 deletions.
There are no files selected for viewing
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -0,0 +1,42 @@ | ||
# Development cycle | ||
|
||
To keep up with the fast development of the Cairo language and Starknet network while maintaining a secure | ||
and healthy development process, **we organize our work in 3-weeks cycles**. | ||
These cycles consist of **milestones** and **sprints.** | ||
|
||
## 📍 Milestones | ||
|
||
A milestone is a set of [issues](https://github.com/OpenZeppelin/cairo-contracts/issues) intended to be addressed. | ||
We usually aim to have at least 4 milestones planned ahead (~12 weeks of work), | ||
enough visibility for users to set realistic expectations on when a feature will be available, | ||
and give us space to gauge demand. | ||
We can also make better decisions and prioritization when we’re mindful of the bigger picture. | ||
|
||
We organize issues in our [Github project](https://github.com/orgs/OpenZeppelin/projects/29) in the following views: | ||
|
||
- [Current milestone](https://github.com/orgs/OpenZeppelin/projects/29/views/2) (now) | ||
- [Next milestone](https://github.com/orgs/OpenZeppelin/projects/29/views/3): ~3 weeks from now | ||
- [After milestone](https://github.com/orgs/OpenZeppelin/projects/29/views/4): ~6 weeks from now | ||
- [Later milestone](https://github.com/orgs/OpenZeppelin/projects/29/views/5): ~9 weeks from now | ||
- [Backlog](https://github.com/orgs/OpenZeppelin/projects/29/views/7): issues not assigned to any milestone | ||
- [Good to tackle](https://github.com/orgs/OpenZeppelin/projects/29/views/10): issues not planned soon nor in progress, for contributors to take | ||
|
||
## 🏁 Sprints | ||
|
||
A sprint is a 3-week period of time in which we intend to complete a milestone. | ||
Some milestones might extend or shorten a little bit if issues are finished ahead or after schedule, | ||
while the end of a sprint marks the time to release whatever work has been finished to date, | ||
i.e. “[the release train departs](https://github.com/OpenZeppelin/cairo-contracts/blob/main/RELEASING.md)”. | ||
|
||
- We design milestones to take ~25 working days so we can tackle them in a single sprint | ||
1. 5 working days * 3 weeks/cycle * 3 devs | ||
- ⇒ 45 workdays/sprint | ||
2. we estimate we spend roughly ~1/3 or our time doing reviews | ||
- ⇒ 30 workdays/sprint | ||
3. we apply a 1/6 reduction to account for vacations, sickness, distractions, support, etc. | ||
- **⇒ 25 workdays/sprint** | ||
- To do so, we categorize issues by size based on a rough estimate of how many working days we expect it to take | ||
- 🦔 tiny: ~0.5 days | ||
- 🐇 small: ~2.5 days | ||
- 🐂 medium: ~5 days | ||
- 🦑 large: ~10 days | ||