Currently, in the culvert capacity workflow, the peak-flow calculation is run for every record in the NAACC table. This calculation includes costly raster operations like delineation and flow length.
In a best-practices data prep workflow, all culverts at a common crossing have been snapped to the same location (flow line) on hydrologically-corrected DEM. That means more every culvert at the same location will have the same peak-flow. We could cut down on geoprocessing time quite a bit for multi-culvert crossing situations if we only run once and then "share" the output with the other culvert records at the same crossing.
There are at least two approaches here:
run peak flow for records in NaaccCrossing model (which includes a list of culverts via NaaccCulvert model).
for this approach to work well, it assumes that all culverts with common Survey_Id have in fact been snapped to the same location. Are there cases where they might not?
analyze geographic coincidence of culverts (using say, the resolution of the DEM as a snapping distance), and use those groups to run peak flow, ignoring any association based on the Survey_Id
this approach potentially would handle situations where there multiple surveys for a crossing
Changing this would require a pretty significant refactor to the existing workflows, but not underlying calculators or lower-level geoprocessing workflows. That refactor may best be able to be implemented in parallel with other tools.
The text was updated successfully, but these errors were encountered:
Currently, in the culvert capacity workflow, the peak-flow calculation is run for every record in the NAACC table. This calculation includes costly raster operations like delineation and flow length.
In a best-practices data prep workflow, all culverts at a common crossing have been snapped to the same location (flow line) on hydrologically-corrected DEM. That means more every culvert at the same location will have the same peak-flow. We could cut down on geoprocessing time quite a bit for multi-culvert crossing situations if we only run once and then "share" the output with the other culvert records at the same crossing.
There are at least two approaches here:
NaaccCrossing
model (which includes a list of culverts viaNaaccCulvert
model).Survey_Id
have in fact been snapped to the same location. Are there cases where they might not?Survey_Id
Changing this would require a pretty significant refactor to the existing workflows, but not underlying calculators or lower-level geoprocessing workflows. That refactor may best be able to be implemented in parallel with other tools.